11/22/2006 |
7:00 PM |
8:00 PM |
1 |
Re-floxed the altered AN4 bolts into the front of the longerons and re-mounted the canard to align same |
|
11/22/2006 |
4:10 PM |
4:39 PM |
0.5 |
Re-drilled holes for lift tab pins in longerons, sanded fuselage top for proper CZNC-12 clearance |
|
11/21/2006 |
7:06 PM |
8:25 PM |
1.3 |
Drilled repaired lift tab for its bushing, cleaned the bushings and pins and floxed the bushings into the lift tabs |
|
11/11/2006 |
2:53 PM |
4:06 PM |
1.2 |
Cleaned out the broken foam from the LH lift tab, made a new one and microed it in |
|
11/4/2006 |
8:10 AM |
9:01 AM |
0.9 |
Finished removing canard from fuselage - damaged one lift tab, NC-2 inserts came out of the lift tabs and the modified AN-3 bolts came out of the longerons |
|
11/3/2006 |
3:37 PM |
4:42 PM |
1.1 |
worked to remove canard from fuselage |
|
10/18/2006 |
6:38 PM |
8:22 PM |
1.7 |
Trimmed the elevator inboard ends, fitted canard and floxed in the alignment pins |
|
9/30/2006 |
9:20 AM |
12:31 PM |
3.2 |
Trimmed the fuselage sides to fit the elevator offset tube, added the 1 ply BID layup to the top of the fuselage "edges" when that was complete |
|
9/27/2006 |
6:26 PM |
7:44 PM |
1.3 |
Trimmed the alignment tabs, drilled them for the CN2 bushings and installed same. Drilled F22 and the lift tab assembly to 1/4" and installed bolts |
|
9/24/2006 |
9:50 AM |
11:31 AM |
1.7 |
Cut notches then did the 4 ply BID layup on the back of the canard top lift tabs |
|
9/19/2006 |
4:36 PM |
5:57 PM |
1.4 |
Epoxied the lift tab foam onto the canard then added the 5 ply BID layup |
|
9/13/2006 |
4:32 PM |
6:08 PM |
1.6 |
Started making tabs for the top of the canard |
|
9/12/2006 |
5:04 PM |
5:44 PM |
0.7 |
Removed canard from fuselage and trimmed flox pads |
|
9/10/2006 |
12:44 PM |
4:44 PM |
4 |
Carved and sanded and filed until the canard was level, perpendicular, etc. then made flox pads for the lift tabs on F22 |
|
9/10/2006 |
10:05 AM |
12:33 PM |
2.5 |
Carved F22 and the fuselage sides to get the canard level, perpendicular and at the right incidence |
|
9/9/2006 |
1:35 PM |
4:54 PM |
3.3 |
Final trimmed around lift tabs, placed canard on fuselage and started leveling and measuring |
|
9/9/2006 |
10:33 AM |
12:22 PM |
1.8 |
Moved fuselage onto jig table and started leveling |
|
4/30/2006 |
3:10 PM |
6:01 PM |
2.9 |
Removed fuselage from rotisserie and made adjustable mounts for installing canard; drilled # 10 holes for alignment pins |